Building Estimation Step by Step In Excel Sheet
Dear friend, we work building quantity calculation in manual in a paper, So now going we area in how to Calculate in Excel use a long wall and short wall method.
This long wall and short wall method is very easy to calculation in the estimation sheet. In this estimation excel sheet easy calution using a excel formulas. In this article also attached construction cost estimate template excel sheet. so please see that.
Laminates contains plastics and resins. Some resins give off harmful gases. In this article, we calculate step by calculation as below.
Note: Free Download building construction estimate spreadsheet excel download UK, US, Canada, and also India.
Table of Contents
Following Quantities Are Building Estimation
- Excavation.
- Footing P.C.C.
- Footing R.C.C.
- Column up to Plinth Level R.C.C.
- Backfilling.
- Plinth Beam R.C.C.
- Grae Slab R.C.C.
- Column Up to Slab Level R.C.C.
- Brick Masonry.
- In Side Plaster.
- Out Side Plaster.
- Celling Plaster.
- Slab R.C.C.
- In Side Paint.
- Out Side Pint.
Building Estimation
It is processed by predicting the probable cost of a project by calculating material quantity and their costing with help of market rates before undertaking any construction project.
Building Estimate Format in Excel, Building Material Calculator Free Download – [button url=”https://drive.google.com/uc?export=download&id=1CkeWNg68pEXU8whEjTZpcKO9GaMA73Zo” target=”self” style=”default” background=”#004D3F” color=”#FFFFFF” size=”3″ wide=”no” center=”no” radius=”auto” icon=”” icon_color=”#FFFFFF” text_shadow=”none” desc=”” download=”” onclick=”” rel=”” title=”” id=”” class=””]Download Excel Sheet[/button]
Building Estimation and Costing Excel Sheet – [button url=”https://drive.google.com/uc?export=download&id=1CkeWNg68pEXU8whEjTZpcKO9GaMA73Zo” target=”self” style=”default” background=”#004D3F” color=”#FFFFFF” size=”3″ wide=”no” center=”no” radius=”auto” icon=”” icon_color=”#FFFFFF” text_shadow=”none” desc=”” download=”” onclick=”” rel=”” title=”” id=”” class=””]Download Excel Sheet[/button]
#1. Excavation
How to Find Excavation as Per Drawing
Footing excavation work needs sum drawing like Footing location Drawing and Section Drawing. All drawing as per below, please see
Section A-A
Footing Location
In this plan, 11 footings as per drawing.
Length = 0.6m + 1.0m + 0.6m = 2.20m
Here 0.6 m is working space in footing for both sides.
And,1.0 m = footing size
As per follows table format copy of the building estimate excel sheet.
[table responsive=”yes” alternate=”yes” fixed=”no” class=””]
QUANTITY SHEET | |||||||
Sr. No. | Item Description | No. | Length (m) |
Widht/ Breadth (m) |
Height/ Depth (m) |
Quantity | Unit |
1 | Earthwork in Excavation in Foundation: |
||||||
Footing (1m x 1m) | 11 | 2.200 | 2.200 | 1.580 | 84.12 | Cu.m. | |
Depth From GL = 0.6 + 1 + 0.6 | |||||||
0.6 =Extra For working space | |||||||
Total Qty= | 84.12 | Cu.m. |
[/table]
#2. Footing P.C.C.
How to Find Footing P.C.C. as Per Drawing
In this plan, 11 footings as per drawing.
Length = 0.15m + 1.0m + 0.15m = 1.30m
Here 0.15 m = P.C.C. working space in footing, for both side
And,1.0 m = footing size
[table responsive=”yes” alternate=”yes” fixed=”no” class=””]
QUANTITY SHEET | |||||||
Sr. No. | Item Description | No. | Length (m) |
Widht/ Breadth (m) |
Height/ Depth (m) |
Quantity | Unit |
2 | Footing P.C.C. | ||||||
Footing (1m x 1m) | 11 | 1.300 | 1.300 | 0.075 | 1.39 | Cu.m. | |
Thickness = 0.075 | |||||||
D = 0.150 + 1.0 + 0.150 | |||||||
Total Qty= | 1.39 | Cu.m. |
[/table]
#3. Footing R.C.C.
How to Find Footing R.C.C. as Per Drawing
In this plan, 11 footings as per drawing.
Length = 1.0m = 1.0m
Here Height = 0.450 m
And, 1.0 m = footing size
[table responsive=”yes” alternate=”yes” fixed=”no” class=””]
QUANTITY SHEET | |||||||
Sr. No. | Item Description | No. | Length (m) |
Widht/ Breadth (m) |
Height/ Depth (m) |
Quantity | Unit |
3 | Footing R.C.C. | ||||||
Base(1m x 1m) | 11 | 1.000 | 1.000 | 0.450 | 4.95 | Cu.m. | |
Thickness = 0.450 | |||||||
Total Qty= | 4.95 | Cu.m. |
[/table]
#4. Column up to Plinth Level R.C.C.
How to Find Column up to Plinth Level R.C.C. as Per Drawing
In this plan, 11 footings as per drawing.
Length = 0.230 m, Breadth = 0.230 m
Here Height = 1.05 m
[table responsive=”yes” alternate=”yes” fixed=”no” class=””]
QUANTITY SHEET | |||||||
Sr. No. | Item Description | No. | Length (m) |
Widht/ Breadth (m) |
Height/ Depth (m) |
Quantity | Unit |
4 | Column up to Plinth Level R.C.C. | ||||||
Column | 11 | 0.230 | 0.230 | 1.050 | 0.61 | Cu.m. | |
Total Qty= | 0.61 | Cu.m. |
[/table]
#5. Backfilling
How to Find Backfilling as Per Drawing
Footing backfilling qty for 11 Qty
Length & Breadth = 2.2 m, Height Footing Bottom to ground level = 1.580 mm
Backfilling = Excavation – Footing P.C.C – Column R.C.C
Plinth Beam Backfilling
Height of backfilling = 0.600 m
Total plinth beam backfilling = Total Area – Plinth beam
[table responsive=”yes” alternate=”yes” fixed=”no” class=””]
QUANTITY SHEET | |||||||
Sr. No. | Item Description | No. | Length (m) |
Widht/ Breadth (m) |
Height/ Depth (m) |
Quantity | Unit |
5 | BackFilling | ||||||
5.a | Backfilling In Footing | ||||||
Excavation Area | 11 | 2.200 | 2.200 | 1.580 | 84.12 | Cu.m. | |
Deduction | |||||||
Footing P.C.C. | -11 | 1.300 | 1.300 | 0.075 | -1.39 | Cu.m. | |
Footing R.C.C. | -11 | 1.000 | 1.000 | 0.450 | -4.95 | Cu.m. | |
Footing Column | -11 | 0.230 | 0.230 | 1.050 | -0.61 | Cu.m. | |
5.a Total Qty= | 77.16 | Cu.m. | |||||
5.b | Plinth Beam Backfilling | ||||||
Plinth area out to out | 1 | 10.240 | 7.690 | 0.600 | 47.25 | Cu.m. | |
Deduction | |||||||
L-1 | -3 | 10.240 | 0.230 | 0.600 | -4.24 | Cu.m. | |
L-2 | -4 | 3.000 | 0.230 | 0.600 | -1.66 | Cu.m. | |
L-3 | -3 | 4.000 | 0.230 | 0.600 | -1.66 | Cu.m. | |
L-4 | -1 | 1.500 | 0.230 | 0.600 | -0.21 | Cu.m. | |
L-5 | -1 | 2.315 | 0.230 | 0.600 | -0.32 | Cu.m. | |
5.b Total Qty= | 39.17 | Cu.m. | |||||
5.a + 5.b Total Qty= | 116.33 | Cu.m. |
[/table]
Also, Read: What Is a Spillway | Types of Spillway | Definition Spillway | Spillway Design
#6. Plinth Beam R.C.C.
How to Find Plinth Beam R.C.C. as Per Drawing
Lintel Beam
As per lintel beam drawing, L-1 = 3 nos., L-2 = 4 nos., L-3 = 3 nos., L- 4 = 1 nos, L-5 = 1 nos of qty and length
and beam size = 0.230 m x 0.600 m
[table responsive=”yes” alternate=”yes” fixed=”no” class=””]
QUANTITY SHEET | |||||||
Sr. No. | Item Description | No. | Length (m) |
Widht/ Breadth (m) |
Height/ Depth (m) |
Quantity | Unit |
6 | Plinth Beam R.C.C. | ||||||
Beam (230 mm x 600 mm) | |||||||
L-1 | 3 | 10.240 | 0.230 | 0.600 | 4.24 | Cu.m. | |
L-2 | 4 | 3.000 | 0.230 | 0.600 | 1.66 | Cu.m. | |
L-3 | 3 | 4.000 | 0.230 | 0.600 | 1.66 | Cu.m. | |
L-4 | 1 | 1.500 | 0.230 | 0.600 | 0.21 | Cu.m. | |
L-5 | 1 | 2.315 | 0.230 | 0.600 | 0.32 | Cu.m. | |
Total Qty= | 0.32 | Cu.m. |
[/table]
#7. Grae Slab R.C.C.
How to Find Grae Slab RCC as Per Drawing
Grae Slab RCC = ( Total Length x Total Breadth x Thickness ) – Column
Grae Slab RCC = ( 10.240 x 7.690 x 0.100 ) – ( 11 x 0.230 x 0.230 x 0.100)
Grae Slab RCC = ( 7.87 ) – (0.06)
Grae Slab RCC = 7.82 Cu.m.
[table responsive=”yes” alternate=”yes” fixed=”no” class=””]
QUANTITY SHEET | |||||||
Sr. No. | Item Description | No. | Length (m) |
Widht/ Breadth (m) |
Height/ Depth (m) |
Quantity | Unit |
7 | Grae Slab R.C.C. | ||||||
Plinth area out to out | 1 | 10.240 | 7.690 | 0.100 | 7.87 | Cu.m. | |
Deduction | |||||||
Column | -11 | 0.230 | 0.230 | 0.100 | -0.06 | Cu.m. | |
Total Qty= | 7.82 | Cu.m. |
[/table]
#8. Column Up to Slab Level R.C.C.
How to Find Grae Slab RCC as Per Drawing
Column Length & Breadth= 0.230 m
Height = Ground Slab – Ground Floor – Slab Beam
Height = 3 – 0 – 0.350 = 2.650 m
[table responsive=”yes” alternate=”yes” fixed=”no” class=””]
QUANTITY SHEET | |||||||
Sr. No. | Item Description | No. | Length (m) |
Widht/ Breadth (m) |
Height/ Depth (m) |
Quantity | Unit |
8 | Column Up to Slab Level R.C.C. | ||||||
Column | 11 | 0.230 | 0.230 | 2.650 | 1.54 | Cu.m. | |
Total Qty= | 1.54 | Cu.m. |
[/table]
#9. Brick Masonry
How to Find Brick Masonry as Per Drawing
Plan
Elevation
Section
Brick masonry calculation uses a Long wall and Short wall method
All length as per drawing and height = 3.00 m – 0.35 m = 2.65 m.
[table responsive=”yes” alternate=”yes” fixed=”no” class=””]
QUANTITY SHEET | |||||||
Sr. No. | Item Description | No. | Length (m) |
Widht/ Breadth (m) |
Height/ Depth (m) |
Quantity | Unit |
9 | Brick Masonry | ||||||
230 mm thick wall Brick Masonry | |||||||
Long Wall | 3 | 10.240 | 0.230 | 2.650 | 18.72 | Cu.m. | |
Shot wall-1 | 3 | 3.000 | 0.230 | 2.650 | 5.49 | Cu.m. | |
Shot wall-1 | 1 | 3.000 | 0.230 | 1.200 | 0.83 | Cu.m. | |
Shot Wall-2 | 3 | 4.000 | 0.230 | 2.650 | 7.31 | Cu.m. | |
Deduction | |||||||
Column | -11 | 0.230 | 0.230 | 2.650 | -1.54 | Cu.m. | |
Window W | -2 | 2.000 | 0.230 | 1.200 | -1.10 | Cu.m. | |
Window W1 | -2 | 1.500 | 0.230 | 1.200 | -0.83 | Cu.m. | |
Window W2 | -3 | 1.200 | 0.230 | 1.200 | -0.99 | Cu.m. | |
Window W3 | -1 | 1.200 | 0.230 | 1.500 | -0.41 | Cu.m. | |
Door o | -2 | 1.200 | 0.230 | 2.100 | -1.16 | Cu.m. | |
Door D | -1 | 1.200 | 0.230 | 2.100 | -0.58 | Cu.m. | |
Door D1 | -1 | 1.000 | 0.230 | 2.100 | -0.48 | Cu.m. | |
Door MS | -1 | 2.000 | 0.230 | 1.200 | -0.55 | Cu.m. | |
Vent | -1 | 0.900 | 0.230 | 0.600 | -0.12 | Cu.m. | |
Vent V1 | -1 | 0.600 | 0.230 | 0.600 | -0.08 | Cu.m. | |
Total Qty 230 mm Thick Wall= | 24.49 | Cu.m. | |||||
115 mm thick wall Brick Masonry | |||||||
Bath Room | 1 | 1.500 | 0.115 | 2.650 | 0.46 | Cu.m. | |
Passage wall | 1 | 2.315 | 0.115 | 2.650 | 0.71 | Cu.m. | |
Deduction | |||||||
Door D2 | -2 | 0.750 | 0.115 | 2.100 | -0.36 | Cu.m. | |
Parapet Wall | |||||||
Long Wall | 2 | 10.240 | 0.115 | 1.000 | 2.36 | Cu.m. | |
Shot Wall | 2 | 7.460 | 0.115 | 1.000 | 1.72 | Cu.m. | |
Total Qty 115 mm Thick Wall= | 4.87 | Cu.m. |
[/table]
#10. In Side Plaster
How to Find In Side Plaster as Per Drawing
Sum Note Point for deduction
- 0.5 sq.m. below section is a full deduction
- 0.5 sq.m. to 3.0 sq.m. between half deduction in area
- 3.0 sq.m above full deduction but add side pattas
[table responsive=”yes” alternate=”yes” fixed=”no” class=””]
QUANTITY SHEET | |||||||
Sr. No. | Item Description | No. | Length (m) |
Widht/ Breadth (m) |
Height/ Depth (m) |
Quantity | Unit |
10 | In Side Plaster | ||||||
Bed Room | |||||||
Long Wall | 2 | 4.000 | 3.000 | 24.00 | Sq.m. | ||
Shot wall | 2 | 3.000 | 3.000 | 18.00 | Sq.m. | ||
Deduction | |||||||
Door D1 | -0.5 | 1.000 | 2.100 | -1.05 | Sq.m. | ||
Window W2 | -0.5 | 1.200 | 1.000 | -0.60 | Sq.m. | ||
Window W3 | -0.5 | 1.200 | 1.200 | -0.72 | Sq.m. | ||
Kitchen + Dining | |||||||
Long Wall | 2 | 4.000 | 3.000 | 24.00 | Sq.m. | ||
Shot wall | 2 | 4.000 | 3.000 | 24.00 | Sq.m. | ||
Deduction | |||||||
Door O | -0.5 | 1.200 | 2.100 | -1.26 | Sq.m. | ||
Window W2 | -1 | 1.200 | 1.000 | -1.20 | Sq.m. | ||
Verandah | |||||||
Long Wall | 2 | 3.000 | 3.000 | 18.00 | Sq.m. | ||
Shot wall | 1 | 3.000 | 3.000 | 9.00 | Sq.m. | ||
Shot wall | 1 | 3.000 | 1.200 | 3.60 | Sq.m. | ||
Deduction | |||||||
Door MS | -0.5 | 1.200 | 1.200 | -0.72 | Sq.m. | ||
Door D | -0.5 | 1.200 | 2.100 | -1.26 | Sq.m. | ||
Window W | -0.5 | 2.000 | 1.200 | -1.20 | Sq.m. | ||
DRG. Room | |||||||
Long Wall | 2 | 5.550 | 3.000 | 33.30 | Sq.m. | ||
Shot wall | 2 | 4.000 | 3.000 | 24.00 | Sq.m. | ||
Deduction | |||||||
Door O | -1 | 1.200 | 2.100 | -2.52 | Sq.m. | ||
Door D | -0.5 | 1.200 | 1.200 | -0.72 | Sq.m. | ||
Window W | -0.5 | 2.000 | 1.200 | -1.20 | Sq.m. | ||
Window W1 | -1 | 1.500 | 1.200 | -1.80 | Sq.m. | ||
Bath Room | |||||||
Long Wall | 2 | 1.500 | 3.000 | 9.00 | Sq.m. | ||
Shot wall | 2 | 1.200 | 3.000 | 7.20 | Sq.m. | ||
Deduction | |||||||
Door D2 | -0.5 | 0.750 | 2.100 | -0.79 | Sq.m. | ||
Vent V1 | -0.5 | 0.900 | 0.600 | -0.27 | Sq.m. | ||
W.C. | |||||||
Long Wall | 2 | 1.500 | 3.000 | 9.00 | Sq.m. | ||
Shot wall | 2 | 1.000 | 3.000 | 6.00 | Sq.m. | ||
Deduction | |||||||
Door D2 | -0.5 | 0.750 | 2.100 | -0.79 | Sq.m. | ||
Vent | -0.5 | 0.600 | 0.600 | -0.18 | Sq.m. | ||
Passage | |||||||
Long Wall | 2 | 2.320 | 3.000 | 13.92 | Sq.m. | ||
Shot wall | 2 | 1.390 | 3.000 | 8.34 | Sq.m. | ||
Deduction | |||||||
Door D2 | -1 | 0.750 | 2.100 | -1.58 | Sq.m. | ||
Door D1 | -1 | 1.000 | 2.100 | -2.10 | Sq.m. | ||
Door O | -1 | 1.200 | 2.100 | -2.52 | Sq.m. | ||
Total Qty In Side Plaster= | 208.89 | Sq.m. |
[/table]
#11. Out Side Plaster
How to Find Out Side Plaster as Per Drawing
[table responsive=”yes” alternate=”yes” fixed=”no” class=””]
QUANTITY SHEET | |||||||
Sr. No. | Item Description | No. | Length (m) |
Widht/ Breadth (m) |
Height/ Depth (m) |
Quantity | Unit |
11 | Out Side Plaster | ||||||
Front Side | 1 | 4.450 | 4.775 | 21.25 | Sq.m. | ||
1 | 3.230 | 2.180 | 7.04 | Sq.m. | |||
Lintel W | 1 | 2.000 | 1.300 | 2.60 | Sq.m. | ||
Deduction | |||||||
Door MS | -0.5 | 1.200 | 1.200 | -0.72 | Sq.m. | ||
Window W | -0.5 | 2.000 | 1.200 | -1.20 | Sq.m. | ||
Back Side | 1 | 7.690 | 4.775 | 36.72 | Sq.m. | ||
Lintel W 2 | 2 | 1.200 | 1.300 | 3.12 | Sq.m. | ||
Deduction | |||||||
Window W 2 | -1 | 1.200 | 1.000 | -1.20 | Sq.m. | ||
Right Side | 1 | 10.240 | 4.775 | 48.90 | Sq.m. | ||
Deduction | |||||||
Window W | -0.5 | 2.000 | 1.200 | -1.20 | Sq.m. | ||
Window W 3 | -0.5 | 1.200 | 1.200 | -0.72 | Sq.m. | ||
Vent | -0.5 | 0.600 | 0.600 | -0.18 | Sq.m. | ||
Vent V1 | -0.5 | 0.900 | 0.600 | -0.27 | Sq.m. | ||
Left Side | 1 | 10.240 | 4.775 | 48.90 | Sq.m. | ||
Deduction | |||||||
Window W 1 | -1 | 1.500 | 1.200 | -1.80 | Sq.m. | ||
Window W 2 | -0.5 | 1.200 | 1.000 | -0.60 | Sq.m. | ||
Parapet Wall | |||||||
Long Wall | 2 | 10.010 | 1.115 | 22.32 | Sq.m. | ||
Shot Wall | 2 | 7.460 | 1.000 | 14.92 | Sq.m. | ||
Total Out Side Plastet Qty = | 197.87 | Sq.m. |
[/table]
#12. Celling Plaster
How to Find Celling Plaster as Per Drawing
[table responsive=”yes” alternate=”yes” fixed=”no” class=””]
QUANTITY SHEET | |||||||
Sr. No. | Item Description | No. | Length (m) |
Widht/ Breadth (m) |
Height/ Depth (m) |
Quantity | Unit |
12 | Celling Plaster | ||||||
Bed Room | 1 | 4.000 | 3.000 | 12.00 | Sq.m. | ||
Kitchen + Dining | 1 | 4.000 | 4.000 | 16.00 | Sq.m. | ||
Verandah | 1 | 3.000 | 3.000 | 9.00 | Sq.m. | ||
DRG. Room | 1 | 5.550 | 4.000 | 22.20 | Sq.m. | ||
Bath Room | 1 | 1.500 | 1.200 | 1.80 | Sq.m. | ||
W.C | 1 | 1.500 | 1.000 | 1.50 | Sq.m. | ||
Passage | 1 | 2.320 | 1.390 | 3.22 | Sq.m. | ||
Total Out Side Plastet Qty = | 65.72 | Sq.m. |
[/table]
#13. Slab R.C.C.
How to Find In Out Slab R.C.C. as Per Drawing
Slab Beam
[table responsive=”yes” alternate=”yes” fixed=”no” class=””]
QUANTITY SHEET | |||||||
Sr. No. | Item Description | No. | Length (m) |
Widht/ Breadth (m) |
Height/ Depth (m) |
Quantity | Unit |
13 | Slab RCC | ||||||
Slab Area | 1 | 10.240 | 7.690 | 0.100 | 7.87 | Cu.m. | |
S-1 | 3 | 10.240 | 0.230 | 0.350 | 2.47 | Cu.m. | |
S-2 | 4 | 3.000 | 0.230 | 0.350 | 0.97 | Cu.m. | |
S-3 | 3 | 4.000 | 0.230 | 0.350 | 0.97 | Cu.m. | |
S-4 | 1 | 1.500 | 0.230 | 0.350 | 0.12 | Cu.m. | |
S-5 | 1 | 2.315 | 0.230 | 0.350 | 0.19 | Cu.m. | |
Total RCC Slab Qty= | 12.59 | Cu.m. |
[/table]
#14. In Side Paint
How to Find In Side Paint as Per Drawing
[table responsive=”yes” alternate=”yes” fixed=”no” class=””]
QUANTITY SHEET | |||||||
Sr. No. | Item Description | No. | Length (m) |
Widht/ Breadth (m) |
Height/ Depth (m) |
Quantity | Unit |
14 | In Side Paint | ||||||
Bed Room | |||||||
Long Wall | 2 | 4.000 | 3.000 | 24.00 | Sq.m. | ||
Shot wall | 2 | 3.000 | 3.000 | 18.00 | Sq.m. | ||
Bed Room Ceiling | 1 | 4.000 | 3.000 | 12.00 | Sq.m. | ||
Deduction | |||||||
Door D1 | -1 | 1.000 | 2.100 | -2.10 | Sq.m. | ||
Window W2 | -1 | 1.200 | 1.000 | -1.20 | Sq.m. | ||
Window W3 | -1 | 1.200 | 1.200 | -1.44 | Sq.m. | ||
Kitchen + Dining | |||||||
Long Wall | 2 | 4.000 | 3.000 | 24.00 | Sq.m. | ||
Shot wall | 2 | 4.000 | 3.000 | 24.00 | Sq.m. | ||
Kitchen + Dining Celling | 1 | 4.000 | 4.000 | 16.00 | Sq.m. | ||
Deduction | |||||||
Door O | -1 | 1.200 | 2.100 | -2.52 | Sq.m. | ||
Window W2 | -2 | 1.200 | 1.000 | -2.40 | Sq.m. | ||
Verandah | |||||||
Long Wall | 2 | 3.000 | 3.000 | 18.00 | Sq.m. | ||
Shot wall | 1 | 3.000 | 3.000 | 9.00 | Sq.m. | ||
Shot wall | 1 | 3.000 | 1.200 | 3.60 | Sq.m. | ||
Verandah Celling | 1 | 3.000 | 3.000 | 9.00 | Sq.m. | ||
Deduction | |||||||
Door MS | -1 | 1.200 | 1.200 | -1.44 | Sq.m. | ||
Door D | -1 | 1.200 | 2.100 | -2.52 | Sq.m. | ||
Window W | -1 | 2.000 | 1.200 | -2.40 | Sq.m. | ||
DRG. Room | |||||||
Long Wall | 2 | 5.550 | 3.000 | 33.30 | Sq.m. | ||
Shot wall | 2 | 4.000 | 3.000 | 24.00 | Sq.m. | ||
DRG. Room Ceiling | 1 | 5.550 | 4.000 | 22.20 | Sq.m. | ||
Deduction | |||||||
Door O | -2 | 1.200 | 2.100 | -5.04 | Sq.m. | ||
Door D | -1 | 1.200 | 1.200 | -1.44 | Sq.m. | ||
Window W | -1 | 2.000 | 1.200 | -2.40 | Sq.m. | ||
Window W1 | -2 | 1.500 | 1.200 | -3.60 | Sq.m. | ||
Bath Room | |||||||
Long Wall | 2 | 1.500 | 3.000 | 9.00 | Sq.m. | ||
Shot wall | 2 | 1.200 | 3.000 | 7.20 | Sq.m. | ||
Bath Room Ceiling | 1 | 1.500 | 1.200 | 1.80 | Sq.m. | ||
Deduction | |||||||
Door D2 | -1 | 0.750 | 2.100 | -1.58 | Sq.m. | ||
Vent V1 | -1 | 0.900 | 0.600 | -0.54 | Sq.m. | ||
W.C. | |||||||
Long Wall | 2 | 1.500 | 3.000 | 9.00 | Sq.m. | ||
Shot wall | 2 | 1.000 | 3.000 | 6.00 | Sq.m. | ||
W.C Celling | 1 | 1.500 | 1.000 | 1.50 | Sq.m. | ||
Deduction | |||||||
Door D2 | -1 | 0.750 | 2.100 | -1.58 | Sq.m. | ||
Vent | -1 | 0.600 | 0.600 | -0.36 | Sq.m. | ||
Passage | |||||||
Long Wall | 2 | 2.320 | 3.000 | 13.92 | Sq.m. | ||
Shot wall | 2 | 1.390 | 3.000 | 8.34 | Sq.m. | ||
Passage Celling | 1 | 2.320 | 1.390 | 3.22 | Sq.m. | ||
Deduction | |||||||
Door D2 | -2 | 0.750 | 2.100 | -3.15 | Sq.m. | ||
Door D1 | -2 | 1.000 | 2.100 | -4.20 | Sq.m. | ||
Door O | -2 | 1.200 | 2.100 | -5.04 | Sq.m. | ||
Total Qty In Side Plaster= | 252.14 | Sq.m. |
[/table]
#15. Out Side Pint
How to Find Out Side Plaster as Per Drawing
[table responsive=”yes” alternate=”yes” fixed=”no” class=””]
QUANTITY SHEET | |||||||
Sr. No. | Item Description | No. | Length (m) |
Widht/ Breadth (m) |
Height/ Depth (m) |
Quantity | Unit |
15 | Out Side Plaster | ||||||
Front Side | 1 | 4.450 | 4.775 | 21.25 | Sq.m. | ||
1 | 3.230 | 2.180 | 7.04 | Sq.m. | |||
Lintel W | 1 | 2.000 | 1.300 | 2.60 | Sq.m. | ||
Deduction | |||||||
Door MS | -1 | 1.200 | 1.200 | -1.44 | Sq.m. | ||
Window W | -1 | 2.000 | 1.200 | -2.40 | Sq.m. | ||
Back Side | 1 | 7.690 | 4.775 | 36.72 | Sq.m. | ||
Lintel W 2 | 2 | 1.200 | 1.300 | 3.12 | Sq.m. | ||
Deduction | |||||||
Window W 2 | -1 | 1.200 | 1.000 | -1.20 | Sq.m. | ||
Right Side | 1 | 10.240 | 4.775 | 48.90 | Sq.m. | ||
Deduction | |||||||
Window W | -1 | 2.000 | 1.200 | -2.40 | Sq.m. | ||
Window W 3 | -1 | 1.200 | 1.200 | -1.44 | Sq.m. | ||
Vent | -1 | 0.600 | 0.600 | -0.36 | Sq.m. | ||
Vent V1 | -1 | 0.900 | 0.600 | -0.54 | Sq.m. | ||
Left Side | 1 | 10.240 | 4.775 | 48.90 | Sq.m. | ||
Deduction | |||||||
Window W 1 | -2 | 1.500 | 1.200 | -3.60 | Sq.m. | ||
Window W 2 | -1 | 1.200 | 1.000 | -1.20 | Sq.m. | ||
Parapet Wall | |||||||
Long Wall | 2 | 10.010 | 1.115 | 22.32 | Sq.m. | ||
Shot Wall | 2 | 7.460 | 1.000 | 14.92 | Sq.m. | ||
Total Out Side Plastet Qty = | 191.18 | Sq.m. |
[/table]
[box title=”FAQ” style=”default” box_color=”#333333″ title_color=”#FFFFFF” radius=”3″ class=”” id=””]
Building Estimation
A building estimator or cost estimator is an individual that quantifies the materials, labor, and equipment needed to complete a construction project. Building cost estimating can concern diverse forms of construction from residential properties to hi-rise and civil works.
Calculated to Estimate
- Estimation is used to predict the answer to a calculation.
- The estimation uses round numbers in a calculation to make it quicker or easier to get an approximate answer.
- For example, if we were to estimate the answer to 11.87 x 4.876. We could use the calculation 10 x 5 = 50.
Estimation of Building
Estimation of A Building With Plan is processed of predicting the probable cost of the project by calculating material quantity and their costing with help of market rates before undertaking any construction project.
Estimate of Building in Excel
Cost Estimation RCC Building Excel Sheet In order to determine the rate of a particular item, the factors affecting the rate of that item are studied carefully and then finally a rate is decided for that item. This process of determining the rates of an item is termed as analysis of rates or rate analysis.
Estimate for Building
Estimation of A Building With Plan is processed of predicting the probable cost of the project by calculating material quantity and their costing with help of market rates before undertaking any construction project.
[/box]
[note note_color=”#F2F2F2 ” text_color=”#333333″ radius=”3″ class=”” id=””]
Like this post? Share it with your friends!
Suggested Read –
- Top 10 Tiles Companies in India 2021
- Density of Cement Sand and Aggregate | Density of Cement | Density of Sand | Density of Aggregate
- What Is Gable Roof | History of Gable Roofing | Gable Roof Design | Parts of Gable Roof | 7 Types of Gable Roofs | How Long Can the Roof Last? | Gable Roof Advantages and Disadvantages | Cost of Gable Roof Construction |
- What Is Plinth | What Is Plinth Beam | What Is Plinth Protection | Purpose of the Plinth Beam in a Structure | Advantages & Disadvantages of Plinth Beam
- Concrete Release Agent | Concrete Form Release Agent | Concrete Formwork Release Agent | Concrete Form Release Oil | Concrete Mold Release Agent | Homemade Concrete Release Agent | Concrete Release Agent for Wood | How to Keep Concrete from Sticking to Wood | Fiberglass Release Agent |
[/note]