What is Rate analysis
|

All About Rate Analysis | What is Rate Analysis | Rate Analysis of Earth Work, Brick, Concrete and Plaster

ALL ABOUT RATE ANALYSIS

What is Rate Analysis?

What is Rate Analysis?

The basis of arriving at a correct and reasonable rate per unit. work or supply for a particular item following its specification and detailed survey of materials, labor, equipment, etc. as required for the unit work and their prevailing rates may be called an analysis of rate.

The procedure of analyzing the rate per unit of an item has been described.

This consists of the following heads:—

  • Quantity of materials required per unit rate of work and its cost delivered at work site including first cost, freight, transportation, sales tax, and insurance charges as artists in question. In case when materials like cement, steel, stone chips, and bitumen are supplied departmentally, then profit on the cost of materials is not allowed, but the cost of carriages from godown to work site shall be added.
  • A number of labor or labor hours required to complete per unit rate of work and its cost.
  • Overhead or equipment and establishment charges are required to complete per unit rate of work.
  • Profit while arriving at workable rates, the factors that are to be considered have already been described.

In this rate analysis, all civil items consider and all items for different rate analyses sum major rate analysis as per below.

  • Rate Analysis of Earth Work.
  • Rate Analysis of Brick.
  • Rate Analysis of Concrete.
  • Rate Analysis of Plaster.

Rate Analysis of Earth Work.

Rate Analysis of Earth Work.

  • As per the below rate analysis of earthwork
  • Earthwork in an excavation in all kinds of soil including banking in 20 cm layers and breaking clods, ramming and dressing up for the purpose of making embankments or filling up ground depressions, lead up to 50 m and lift up to 1.50 m.
  • As per CPWD minimum labor requirement of 1 cu.m. excavation man labor is 0.21 per day and female labor 0.14 per day.
  • Required other charges 2 %, Add for Water Charge @ 1% on Items Marked, Add for Contractor’s Profit @15% on Items Marked.
  • For all Calculations for reading click here.

[su_table responsive=”yes” alternate=”no”]

Sr No. Description Qty Unit Rate Cost
Details of cost for 28.34 Cu.m.
A Labour Charges
1 Man Labour 6 Day 400 2400
2 Female Labour 4 Day 350 1400
B Other Charges 2 % Extra 76
C Add for Water Charge @ 1% on Items Marked 38
D Add for Contractor’s Profit @15% on Items Marked 570
Cost of 28.34 Cu.m. 4484
Cost of Cu.m. 158.22
Round off Cu.m. 158

[/su_table]

Rate Analysis of Brick.

  • As per the below rate analysis of brick
  • Brickwork with best available local bricks in foundation and plinth in cement mortar 1:3 (1
    cement : 3 fine sand)
  • Rate analysis of Brickwork minimum labor requirement 10 cu.m. as below Bhisti 1.80 nos, Coolie 10.00 nos, Mason 3.3 nos, and Helper 3.3 nos. this above labor calculation use experience is also recommended by CPWD
  • Required other charges 2 %, Add for Water Charge @ 1% on Items Marked, Add for Contractor’s Profit @15% on Items Marked, Transportation Cost 1%, Scaffolding 1% Extra.
  • All Calculations for reading Clicks are here.

[su_table responsive=”yes” alternate=”no”]

Sr No. Description Qty Unit Rate Cost
Brickwork with best available local bricks in foundation and plinth in cement mortar 1:3 (1 cement : 3 fine sand)
Details of cost for 10.00 Cu.m.
A Labour Charges
1 Baathist 1.8 Day 350 630
2 Coolie 10 Day 350 3500
3 Mason 3.3 Day 700 2310
4 Helper 3.3 Day 350 1155
B Material
1 Bricks 4940 Nos 5 24700
2 Cement 21 Bag 280 5880
3 Sand 2.8 Cu.m. 850 2380
C Scaffolding 1% Extra 1% 329.6
D Transportation Cost 1% 1% 329.6
E Other Charges 2 % Extra 2% 659.2
F Add for Water Charge @ 1% on Items Marked 1% 329.6
G Add for Contractor’s Profit @15% on Items Marked 15% 4944
Cost of 10.00 Cu.m. 47147
Cost of Cu.m. 4714.7
Round off Cu.m. 4715

[/su_table]

Rate Analysis of Concrete.

Rate Analysis of Concrete.

  • As per the below rate analysis of concrete
  • Providing and laying in foundations and plinth cement concrete 1: 5: 10 (1 cement: 5 coarse sand: 10 graded stone aggregate 20 mm nominal & 40mm size) excluding the cost of centering and shuttering.
  • Required other charges 2 %, Add for Water Charge @ 1% on Items Marked, Add for Contractor’s Profit @15% on Items Marked,
  • Transportation Cost 1%, Wastage Extra Total Cost of 5%.
  • For all Calculations for reading click here.

[su_table responsive=”yes” alternate=”no”]

Sr No. Description Qty Unit Rate Cost
Providing and laying in foundations and plinth cement concrete 1: 5: 10 (1 cement: 5 coarse sand: 10 graded stone aggregate 40 mm & 20 mm nominal size) excluding the cost of centering and shuttering.
Details of cost for 10.00 Cu.m.
A Labour Charges
1 Baathist 2.7 Day 350 945
2 Coolie 6 Day 350 2100
3 Balder 9 Day 350 3150
4 Mason 0.5 Day 700 350
5 Helper 0.5 Day 400 200
6 Mate 0.4 Day 500 200
B Material
Cement 18 Bag 280 5040
Sand 3.13 Cu.m. 850 2656.25
Aggregate 6.25 Cu.m. 735 4593.75
C Wastage Extra Total Cost of 5% 5% 961.75
D Transportation Cost 1% 1% 122.9
E Other Charges 2 % Extra 2% 245.8
F Add for Water Charge @ 1% on Items Marked 1% 122.9
G Add for Contractor’s Profit @15% on Items Marked 15% 1843.5
Cost of 10.00 Cu.m. 22531.85
Cost of Cu.m. 2253.19
Round off Cu.m. 2253

[/su_table]

Rate Analysis of Plaster.

Rate Analysis of Plaster.

  • As per the below rate analysis of plaster
  • Providing and laying in 12 mm thick plasterwork 1: 4 (1 cement: 4 coarse sand: 1) excluding the cost of with material.
  • For all Calculations for reading click here.

[su_table responsive=”yes” alternate=”no”]

Sr No. Description Qty Unit Rate Cost
Providing and laying in 12 mm thick plasterwork  1: 4 (1 cement: 4 coarse sand: 1) excluding the cost of with material.
Details of cost for 100.00 sq.m.
A Labour Charges
1 Mason 6.7 Day 700 4690
2 Bhisti 9.2 Day 400 3680
3 Coolie 7.5 Day 400 3000
B Material
Cement 9 Bag 280 2520
Sand 1.248 Cu.m. 850 1060.8
C Wastage of Material 2% 2% 71.62
D Scaffolding 1% Extra 1% 35.81
E Transportation Cost 1% 1% 35.81
F Other Charges 2 % Extra 2% 71.62
G Add for Water Charge @ 1% on Items Marked 1% 35.81
Cost of 100.00 Sq.m. 15738.58
Cost of Sq.m. 157.39
Round off Sq.m. 157

[/su_table]

[su_note note_color=”#F2F2F2 ” text_color=”#333333″ radius=”3″ class=”” id=””]